Project

Victor Boin Swimming Pool

Flat roofs

The new roof structure was carefully constructed with a focus on durability and performance. First, a vapor barrier was installed, followed by a layer of cellular glass insulation, a material known for its compressive strength and water resistance. Finally, the entire structure was finished with a two-layer waterproofing system, which provides long-lasting protection against the elements.

Commissioned by the municipality of Saint-Gilles and in collaboration with general contractor ACH Construct, this project helps preserve the distinctive character of this swimming pool while meeting today’s standards for comfort and sustainability.

Any future project on the horizon?
Let's build together

In the heart of Saint-Gilles, the iconic Victor Boin swimming pool is embarking on a new chapter. This famous Brussels landmark, with its rich history, is currently undergoing a thorough renovation to prepare it for the future.

Tectum Group responsible for the renovation of the flat roofs, which cover a total area of approximately 1,800 m². The work began in 2024 and is now in its final stages.

Project Sheet
Location
Saint-Gilles
Construction period
2024–2026
Services
Flat roofs
Roof area
1,800 square meters
Category
Public
Client
Sint-Gillis Municipal Council
Head contractor
ACH Construct
Architect
Stability

The new roof structure was carefully constructed with a focus on durability and performance. First, a vapor barrier was installed, followed by a layer of cellular glass insulation, a material known for its compressive strength and water resistance. Finally, the entire structure was finished with a two-layer waterproofing system, which provides long-lasting protection against the elements.

Commissioned by the municipality of Saint-Gilles and in collaboration with general contractor ACH Construct, this project helps preserve the distinctive character of this swimming pool while meeting today’s standards for comfort and sustainability.

No items found.
Any future project on the horizon?
Let's build together

In the heart of Saint-Gilles, the iconic Victor Boin swimming pool is embarking on a new chapter. This famous Brussels landmark, with its rich history, is currently undergoing a thorough renovation to prepare it for the future.

Tectum Group responsible for the renovation of the flat roofs, which cover a total area of approximately 1,800 m². The work began in 2024 and is now in its final stages.

Any future project on the horizon?
Let's build together

Discover more projects